Sydney Light Rail - Lilyfield Maintenance Depot
The Sydney Light Rail - Lilyfield Maintenance Depot Project consisted of maintaining and densifying the control network,
bulk earthworks volumes, installation of 500m of drainage culverts,90+ drainage pits, 130+ CSR and Electrical pits and routes, 1.1 kilometres of track slab rail pavement and rail installation, 8 turnouts, Fire and Water Mains, 1 HV Substation, 3600msq maintenance building including three embedded rail tracks and three pedestal mounted rail tracks, five gantry cranes, 1km of road pavements, carpark, 1.5km of kerb and gutter,
bulk earthworks volumes, installation of 500m of drainage culverts,90+ drainage pits, 130+ CSR and Electrical pits and routes, 1.1 kilometres of track slab rail pavement and rail installation, 8 turnouts, Fire and Water Mains, 1 HV Substation, 3600msq maintenance building including three embedded rail tracks and three pedestal mounted rail tracks, five gantry cranes, 1km of road pavements, carpark, 1.5km of kerb and gutter,